Project GOTChA chart
This quad chart gives a snapshot of the planned activities for the term, at a high level. This information is presented here in the form of a GOTChA chart.
Goals
- Build an integrated team (SCI-Arc + Caltech) that can win the 2011 Solar Decathlon
- Complete the design development phase of the Solar Decathlon competition and submit design documents on time
- Evaluate and explore options for providing some technology sizzle in our design
|
Technical Challenges
- Bring 20-30 new Caltech students from diverse backgrounds and skill levels up to speed quickly
- Integration of SCI-Arc and Caltech activities (people, goals, schedule, deliverables)
- Some existing baseline designs are not very complete; need more work and re-validation
- Some subsystems have no baseline design
|
Objectives
- Assign students to subsystems and teams, with linkages between teams with overlapping functionality or interfaces
- For subsystems with existing baseline designs:
- Revalidate the baseline design computations and verify that baseline can achieve maximum points for relevant competition(s)
- Communicate and agree on specifications and choices with IPT and SCI-Arc teams
- Perform model-based analysis of system performance in a form that can be used for trade-off studies
- Document the baseline design in a manner that is compatible with design development phase deliverable
- Evaluate technology options that can be incorporated into our design and perform cost analysis for each
- For subsystems without existing baseline designs:
- Analyze options design with performance, cost, electrical load, thermal load estimates
- Establish a baseline design that can achieve maximum points for relevant competition(s), in agreement with IPT and SCI-Arc teams
- Document the baseline design in a manner that is compatible with design development phase deliverable
- Develop and maintain system-level cost and energy budgets and use these to verify ability to maximize points on engineering-driven competitions
- Provide a design capable of full capability (max points) with net-zero energy consumption for 95th percentile day
- Provide a design capable of 90% max points on worst case day (over last 20 years)
|
Approach
- Stick to summer 2010 system architecture decisions; avoid re-inventing the wheel
- Hold off on alterations to the baseline until we have a fully analyzed, documented and costed baseline
- Schedule planning event with Caltech + SCI-Arc to help people meet each other and align goals, milestones and schedule
- Make use of the project wiki as a mechanism to document and enhance team communication
- Identify individual students who will be responsible for insuring good cross-project integration between appropriate groups
- Develop analytical or computational models demonstrating that specifications can be met
- Milestones
- 13 Oct: each subsystem team knows what SD rules apply to their subsystem + understand existing baseline design
- 27 Oct: revalidated/preliminary baseline design computations for each subsystem (depending on initial state); shared decision making between SCI-Arc and Caltech
- 10 Nov: rigorously analyzed and documented baseline designs complete for all subsystems
- 23 Nov: design development documentation complete and delivered to DOE
- 10 Dec: final reports for each student due, with complete subsystem documentation available on project wiki
|
Course schedule
Week |
Date |
Topic |
Reading/Activities |
Homework
|
1
|
27 Sep (M)
|
Organizational meeting
- Reed: Solar Decathlon overview [15 min]
- Fei: Baseline overview [15 min]
- Richard: CS/EE/ME 75 organization [20 min]
- Q&A [5 min]
|
- Submit signup and scheduling sheet by Wed @ noon to box outside 109 Steele
- Read SD rules and baseline design descriptions (see HW #1)
- Team assignments (required for HW #1) will be available by Thursday (30 Sep)
|
HW #1
- SD competition rules
- Subsystem baseline description
- Wiki user page creation
|
2
|
4 Oct (M)
|
Project schedule
- Overall SD schedule [Reed]
- SCI-Arc/Caltech master schedule for fall [Reed]
- GOTChA charts [Richard]
- Milestone "party" (9 Oct?)
|
Team meetings start. Joint scheduling event with Sci-Arc on 9 Oct (?)
|
HW #2: Team schedules, subsystem GOTChAs
|
3
|
11 Oct (M)*
|
System specifications
- Baseline specifications [Fei]
- Documentation format [Reed]
|
|
HW #3: Project specifications
|
4
|
18 Oct (M)
|
System modeling
|
|
HW #4: Baseline model and analysis
|
5
|
25 Oct (M)*
|
Design review process
|
Design reviews (midterms)
|
|
6
|
1 Nov (M)
|
Team presentation
|
|
|
7
|
8 Nov (M)*
|
Team presentation
|
|
|
8
|
15 Nov (M)*
|
Team presentation
|
|
Design review
|
9
|
22 Nov (M)
|
Project review
|
Building information model, design drawings and project manual due
|
|
10
|
29 Nov (M)
|
Lessons learned and plans for second term
|
|
Project documentation due (end of finals)
|